We were delighted at the prospect of becoming a service provider to one of the major aggregate producers here in the UK.
Equally we were keen to show our ability to design, produce and deliver to their stringent timelines whilst coordinating a third party installation contractor.
We had sourced and recommended the installation contractor as someone we had previously worked with and could confidently go forward with.
Logistically we carefully planned how eight articulated vehicles could be loaded at our manufacturing plant in Rochdale, Lancashire and unloaded on site in Cumbria “some 100 miles away” on five consecutive days within the short daylight hours of December.